At the end of September, another important milestone was reached on our construction site: the steel structure, including the false ceiling, has been completed. This means that the load-bearing framework of the hall is now in place – a significant moment, as it is now clear for the first time what dimensions the new building will take on.
Immediately afterwards, work began on installing the hall walls, which give the building its characteristic appearance.
The next step is the steel framework for the administration building. Step by step, our new production hall and the adjacent administration building are growing – and with them, the anticipation of moving in.